The HCMC government’s newly-announced plan to
build several thousands of condos to replenish the resettlement housing fund is
predicted to face uncertainty given the presence of several large-scale
apartment schemes still mired in slow execution.
With
the program to construct 12,500 resettlement apartments, the municipal
authority has urged the Department of Construction to review the actual situation
and assess the implementation progress of on-going resettlement housing
projects. The department needs to submit to the local authority solutions to
select investors and suitable investment methods in a bid to complete the plan
by late next year.
The local
authority has also told the construction department to carry out a program to
build 11,000 resettlement apartments in the south of the city. It is expected
30 hectares will be set aside for high-rise condo building development in in
Nha Be and Binh Chanh districts.
Developers
have been asked to advance their finances to build these schemes and to sell
their resettlement housing funds to local authorities later.
Old projects still foot-dragging
In
early September in 2009, 21st Century International Development Co. started
work on a resettlement project of 4,200 flats in Binh Khanh Ward in HCMC’s
District 2. Covering about 30 hectares, the US$350 million scheme comprises 10
blocks of 20-25 stories.
The
Binh Khanh resettlement project is considered one of the three biggest planned
projects in the city, with 12,500 condos used for the resettlement purpose in
the new urban area Thu Thiem. Once the scheme is complete, the investor is
entitled to use one part of the housing and land fund there for its own business.
The
project owner said at the ground-breaking time it would finish the project
after 30 months of construction to meet the accommodation demand for some
16,000 residents. However, the project has had no progress over the last two
years.
The
same situation is also seen at the project to improve urban quality near Thu
Thiem Bridge on Nguyen Huu Canh Street in Binh Thanh District invested by
Construction JSC No. 5.
The
project includes apartment and leasing office buildings of 35 stories and a
resettlement condo building of 24 floors with a total of 500 flats. The
construction of the scheme has still fallen behind schedule even though it was
planned to be implemented from 2007 to 2015.
Dinh
Dung - The Saigon Times Daily
Business & Investment Opportunities
YourVietnamExpert is a division of Saigon Business Corporation Pte Ltd, Incorporated in Singapore since 1994. As Your Business Companion, we propose a range of services in Consulting, Investment and Management, focusing three main economic sectors: International PR; Healthcare & Wellness;and Tourism & Hospitality. We also propose Higher Education, as a bridge between educational structures and industries, by supporting international programs. Sign up with twitter to get news updates with @SaigonBusinessC. Thanks.